Optimization of our automatic inventory: the dismantling of bridge 885

🚧🔧 Optimization of our automatic inventory: the dismantling of bridge 885, a project successfully completed to reach new heights!

From 2 to 7 January 2025, we launched the project to dismantle bridge 885 mobilising several internal teams: EAI, Methods, Safety, Production, Supply Chain and Purchasing.

The goals :
✅ To store around 100 additional reels on site, thereby reducing external storage
✅ To create 6 metres of track for bridge 886
✅ To dismantle the bridge quickly while limiting the impact on production
✅ To simplify flows and reduce waste
This project was completed a day ahead of schedule, thereby minimising the impact on production!

Thanks to our partner IMECO whose expertise made this project a success.